A and B together can do a piece of work in 30 days. B and C together can do it in 20 days. A starts the work and works on it for 5 days, then B takes up and works for 15 days. Finally C finishes the work in 18 days. The number of days in which C alone can do the work when doing it separately is

a

120 days

b

24 days

c

60 days

d

40 days

Answer : Option B
Explanation :
Let C complete the work in x days. \therefore B’s 1 day’s work =1201x=\frac{1}{20}-\frac{1}{x} and, A’s 1 day’s work =2360+1x=1x160=\frac{2-3}{60}+\frac{1}{x}=\frac{1}{x}-\frac{1}{60} According to the question, 5(1x160)+15(1201x)+18x=15\left(\frac{1}{x}-\frac{1}{60}\right)+15\left(\frac{1}{20}-\frac{1}{x}\right)+\frac{18}{x}=1 5x112+152015x+18x=1\Rightarrow \frac{5}{x}-\frac{1}{12}+\frac{15}{20}-\frac{15}{x}+\frac{18}{x}=1 5x15x+18x=1+11234\Rightarrow \frac{5}{x}-\frac{15}{x}+\frac{18}{x}=1+\frac{1}{12}-\frac{3}{4} (515+18x)=12+1912\Rightarrow\left(\frac{5-15+18}{x}\right)=\frac{12+1-9}{12} 8x=13\Rightarrow \quad \frac{8}{x}=\frac{1}{3} x=8×3=24\Rightarrow \quad x=8 \times 3=24 days Alternative: According to the question, (A + B) × 30 = (B + C) × 20 = 5A + 15B + 18C Now, (A+B)×30=(B+C)×20\Rightarrow(\mathrm{A}+\mathrm{B}) \times 30=(\mathrm{B}+\mathrm{C}) \times 20 3 A+B=2(i)3 \mathrm{~A}+\mathrm{B}=2 \quad \ldots \ldots(\mathrm{i}) (B+C)×20=5 A+15 B+18C\Rightarrow(\mathrm{B}+\mathrm{C}) \times 20=5 \mathrm{~A}+15 \mathrm{~B}+18 \mathrm{C} 5 A5 B=2C5 \mathrm{~A}-5 \mathrm{~B}=2 \mathrm{C} \quad \ldots \ldots (ii) (A+B)×30=5 A+15 B+18C\Rightarrow(\mathrm{A}+\mathrm{B}) \times 30=5 \mathrm{~A}+15 \mathrm{~B}+18 \mathrm{C} 25 A+15 B=18C25 \mathrm{~A}+15 \mathrm{~B}=18 \mathrm{C} \quad \ldots \ldots (iii) From equation (i) and (ii) 2A = 6B AB=31\frac{\mathrm{A}}{\mathrm{B}}=\frac{3}{1} Now equation (i) 3 × 3 + 1 = 2C

∴ Total work = (3 +1) × 30 = 120

Time taken by C\mathrm{C} alone to complete the work

= Total work  Efficiency of C=\frac{\text { Total work }}{\text { Efficiency of } \mathrm{C}}

=1205=24=\frac{120}{5}=24 days