A, B and C together can complete a work in 20 days. A and B together can complete the same work in 30 days. Then C alone can complete the same work in how many days?
Answer : Option D
Explanation : ’s 1 day’s work ’s 1 day’s work C’s 1 day’s work Required time days.
Alternative: 
Efficiency of unit
Time taken by days