A can do a piece of work in 20 days, which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in
Answer : Option B
Explanation : work done by in 9 days Remaining work Time taken by days
Alternative: 
Work done by B in 9 days
= 9 × 5 = 45
Remaining work = 60 – 45 = 15
Time taken by A to complete the remaining work
days