Keerthana
Posted on

A can do a piece of work in 20 days, which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in

a

3 days

b

5 days

c

7 days

d

11 days

Answer : Option B
Explanation :
work done by B\mathrm{B} in 9 days =912=34=\frac{9}{12}=\frac{3}{4} Remaining work =134=14=1-\frac{3}{4}=\frac{1}{4} \therefore Time taken by A=14×20=5\mathrm{A}=\frac{1}{4} \times 20=5 days Alternative:

Work done by B in 9 days

= 9 × 5 = 45

Remaining work = 60 – 45 = 15

Time taken by A to complete the remaining work

=153=5=\frac{15}{3}=5 days

Rate This:
NaN / 5 - 1 votes
Profile photo for Dasaradhan Gajendra